H.B.M.I. Pty Ltd Quarry Expansion, Leslie Vale


EPA Assessment Complete


The Proposal
Public Exhibition of Documentation and Public Representations
Development Proposal and Environmental Management Plan
Environmental Assessment Report and EPA Decision
For Further Information


The Proposal

H.B.M.I. Pty Ltd has proposed to increase production rates of rock products at their Leslie Vale Quarry from 750,000 to 1 million tonnes (563,000m) per annum.

The proponent has lodged a Development Application with a supporting Development Proposal and Environmental Management Plan (DPEMP) to Kingborough Council.

The application was referred to the Board of the Environment Protection Authority (the Board) for assessment under the Environmental Management and Pollution Control Act 1994 (EMPCA).


Public Exhibition of Documentation and Public Representations

A copy of the permit application, and of all plans and other documentation submitted with the permit application (including the DPEMP) were made available for public inspection and may be examined during normal business hours at:

Following the public comment period the proponent was required by the Board to prepare a DPEMP Supplement to address issues raised in public and government agency consultation.


Development Proposal and Environmental Management Plan

The purpose of the DPEMP is to provide a source of information upon which interested individuals, groups, government agencies and the Board may consider the environmental and planning impacts of the proposal.

The DPEMP was prepared by the proponent on the basis of the project specific guidelines for preparation of an DPEMP which were provided by the Board.

HBMI Pty Ltd Leslie Vale Quarry Expansion, DPEMP and Appendices 1-1a

Appendix 1 - Dust Emission Report

Appendix 1a - Dust Management Plan

HBMI Pty Ltd Leslie Vale Quarry Expansion, DPEMP Appendices 2 to 8

Appendix 2 - Stormwater Calculations

Appendix 3 - Air Blast Study

Appendix 3a - Blast Management Plan White Rock Quarry

Appendix 4 - Noise Study

Appendix 5 - Hazard Analysis

Appendix 6 - Response to Kingborough Planning Scheme 2000

Appendix 7 - Eagle Assessment

Appendix 8 - Weed and Disease Management Plan

HBMI Pty Ltd Leslie Vale Quarry Expansion, DPEMP Appendices 9 to 11

Appendix 9 - Traffic Impact Assessment

Appendix 10 - Resource Management Plan

Appendix 11 - Overburden Stockpile Monitoring Plan

HBMI Pty Ltd Leslie Vale Quarry Expansion, DPEMP Supplement


Environmental Assessment Report and EPA decision

The environmental assessment report has now been completed and can be viewed below. This report contains an environmental assessment and recommendations to the Board in relation to the proposal. The permit conditions required by the Board to be included in the land use permit, if a permit is granted, by Kingborough Council are contained in the environmental assessment report.