BOC Ltd - Liquid Natural Gas Plant Westbury


EPA assessment complete


The Proposal
Public Exhibition of Documentation and Public Representations
Development Proposal and Environmental Management Plan
Environmental Assessment Report and EPA Decision
For Further Information


The Proposal

BOC Ltd proposed to construct and operate a Liquid Natural Gas (LNG) plant at the Westbury Industrial Precinct. The project involves using natural gas from the Tasmanian Gas Pipeline to produce approximately 50 tonnes per day of LNG for use as a heavy vehicle fuel.

The application was referred to the Board of the Environment Protection Authority (the Board) for assessment under the Environmental Management and Pollution Control Act 1994 (EMPCA).

BOC Ltd lodged a Development Application with a supporting Development Proposal and Environmental Management Plan (DPEMP) to the Meander Valley Council.

The purpose of the DPEMP is to provide a source of information upon which interested individuals, groups, government agencies, and the Board may consider the environmental and planning impacts of the proposal.

The DPEMP was prepared by the proponents on the basis of the project specific guidelines for preparation of a DPEMP which were provided by the Board.


Public Exhibition of Documentation and Public Representations

Public Exhibition of Documentation

A copy of the permit application, and of all plans and other documentation submitted with the permit application (including the DPEMP) were advertised for public comment. The public comment period is now closed.


Development Proposal and Environmental Management Plan

BOC Ltd - LNG Plant Westbury - DPEMP

Appendices

BOC Ltd - Appendix A - General Project Guidelines

BOC Ltd - Appendix B - Project Specific Guidelines

BOC Ltd - Appendix C - Air Quality Assessment (no Figures)

BOC Ltd - Appendix C - Air Quality Assessment (Figures 1-7)

BOC Ltd - Appendix C - Air Quality Assessment (Figures 8-14)

BOC Ltd - Appendix D - Noise Impact Assessment

BOC Ltd - Appendix E - Flora Values Report

BOC Ltd - Appendix F - Traffic Assessment

BOC Ltd - Appendix G - Planning Scheme Considerations

BOC Ltd - Appendix H - Hazard Risk Assessment

BOC Ltd - Appendix I - General Location Map

BOC Ltd - Appendix J - Site HSE Plan and Condition of Readiness

BOC Ltd - Appendix K - Certificate of Title


Environmental Assessment Report and EPA decision

The environmental assessment report (EAR) has now been completed and can be viewed below. This report contains an environmental assessment and recommendations to the Board in relation to the proposal.

The permit conditions required by the Board to be included in the land use permit, if a permit is granted, by Meander Valley Council are contained in Appendix 3 of the environmental assessment report.

BOC Ltd - LNG Plant Westbury - EAR

Assessments Section
GPO Box 1751
Hobart TAS 7001
Phone: 03 6165 4599 Fax: 03 6173 0254
Email: EPAenquiries@epa.tas.gov.au