• EPA Tasmania
  • Assesment
  • Regulation & Assessment
  • Sustainability
  • Policy & Legislation

Mr Richard Sattler, Anderson Bay Sand Extraction Project, Increase in Production, Waterhouse Road, Bridport


EPA Assessment Closed


The Proposal
Public Exhibition of Documentation
Development Proposal and Environmental Management Plan
Supplement
Environmental Assessment Report and EPA Decision
For Further Information


The Proposal

The application is for an increase in the production limit at the Anderson Bay sand extraction project, up to 1,250,000 cubic metres per annum of sand extracted and screened, from within mining lease 1957P/M, accessed from Waterhouse Road north-east of Bridport. The application also included the development of infrastructure to support an offshore sand loading facility, which is contained within mining lease 2007P/M.

The application is for all works inland from the low water mark and on certificates of title 130153/2, 242847/1 and 244898/2.

The proponent had lodged a Permit Application with a supporting Development Proposal and Environmental Management Plan (DPEMP) to Dorset Council.

The application was referred to the Board of the Environment Protection Authority (the Board) for assessment under the Environmental Management and Pollution Control Act 1994 (EMPCA).‚Äč


Public Exhibition of Documentation

A copy of the permit application and all plans and other documentation submitted with the permit application (including the DPEMP) were made available for public inspection. The public comment period is now closed.


Development Proposal and Environmental Management Plan

The purpose of the DPEMP is to provide a source of information upon which interested individuals, groups, government agencies and the Board may consider the environmental impacts of the proposal.

The DPEMP was prepared by the proponent on the basis of the Project Specific Guidelines for preparation of a DPEMP which were provided by the Board.

Mr Richard Sattler, Anderson Bay Sand Extraction Project, Increase in Production - DPEMP.pdf

Mr Richard Sattler, Anderson Bay Sand Extraction Project, Increase in Production - Appendix A Guidelines.pdf

Mr Richard Sattler, Anderson Bay Sand Extraction Project, Increase in Production - Appendix B Hydrogeological Investigations.pdf

Mr Richard Sattler, Anderson Bay Sand Extraction Project, Increase in Production - Appendix C North Barker Flora and Fauna.pdf

Mr Richard Sattler, Anderson Bay Sand Extraction Project, Increase in Production - Appendix E Vipac Noise Report.pdf


Supplement

Submitted in response to the Boards call for further information following the public comment period.

  Mr Richard Sattler, Anderson Bay Sand Extraction Project, Increase in Production - Supplement Part 1   (1Mb)

  Mr Richard Sattler, Anderson Bay Sand Extraction Project, Increase in Production - Supplement Part 2   (4Mb)


Environmental Assessment Report and EPA decision

The environmental assessment report has now been completed and can be viewed below. The report contains the permit conditions required by the Board to be included in the land use permit, if a permit is granted, by Council.

  Mr Richard Sattler, Anderson Bay Sand Extraction Project, Increase in Production - EAR   (4Mb)


Assessments Section
GPO Box 1751
Hobart TAS 7001
Phone: 03 6165 4599 Fax: 03 6173 0254
Email: Enquiries@epa.tas.gov.au