The Proposal
Stornoway Quarrying proposed to increase production at their existing Raeburn quarry, off Hobart Road Breadalbane, to 210,000 cubic metres of product per annum. The operation would include the use of blasting. It was also proposed to recycle building materials and soils.
The application was referred to the Board of the Environment Protection Authority (the Board) for assessment under the Environmental Management and Pollution Control Act 1994 (EMPCA).
The proponent lodged a Development Application with a supporting Development Proposal and Environmental Management Plan (DPEMP) to the Northern Midlands Council.
The DPEMP was prepared by the proponent on the basis of the project specific guidelines for preparation of a DPEMP which were provided by
the Board.
Public Exhibition of Documentation and Public Representations
Public Exhibition of Documentation
A copy of the permit application, and of all plans and other documentation submitted with the permit application (including the
DPEMP) were advertised for public comment. The public comment period is now closed.
Following the public comment period the proponent was required by the Board to prepare a DPEMP Supplement to address issues raised in public
and Government Agency consultation.
Development Proposal and Environmental Management Plan
Stornoway Raeburn DPEMP (9Mb)
Stornoway - Appendix A - DPEMP Guidelines (219Kb)
Stornoway - Appendix B - Quarry Code of Practice (1Mb)
Stornoway - Appendix C - Traffic Assessment (1Mb)
Stornoway - Appendix D - Stornoway Policies (355Kb)
Stornoway - Appendix E - Rehab Guidelines (953Kb)
Stornoway - Appendix F - PC and Weeds (607Kb)
Stornoway - Appendix G - Aboriginal Cultural Heritage Survey (608Kb)
Stornoway - Appendix H - Terrock Blasting Report (3Mb)
Stornoway - Appendix I - Vipac Noise Assessment (733Kb)
Stornoway - Appendix J - Washdown Guidelines (193Kb)
Stornoway - Appendix K - DPEMP Supplement Jan 2010 (3Mb)
Stornoway - Appendix L - EPA Assessment Report (2Mb)
Stornoway - Supplement - 4 August 2010 (360Kb)
Environmental Assessment Report and EPA decision
The environmental assessment report (EAR) has now been completed and can be viewed below. This report contains an environmental assessment
and recommendations to the Board in relation to the proposal.
The permit conditions required by the Board to be included in the land use permit, if a permit is granted, by Northern Midlands Council
are contained in Appendix 3 of the environmental assessment report.
Stornoway Raeburn EAR - August 2010 (11Mb)