Forico Pty Limited, Hummocks Quarry, Upgrade from Level 1 to Level 2 activity

Current Stage

Public Comment Closed on Case for Assessment

Proposal Details

Client: Forico Pty Limited

Premises: Hummocks Quarry

Activity: Quarry and Materials Handling

Class of Assessment: 2A

Important Dates

Assessment Commenced: 23/3/2022

Case for Assessment Opened for Public Comment: 16/9/2026

Case for Assessment Closed for Public Comment: 30/9/2026

​​​​The Proposal

The proposal is for an increase in production of rock and gravel (extraction and crushing/screening) to 10,000 cubic metres per annum produced. The quarry is located within private timber reserve land and the product will be used for road construction and maintenance. Drilling and blasting will be required to win material.  ​​

The proponent has lodged a Permit Application with a supporting Environmental Effects Report (EER) to Waratah-Wynyard Council.

The application was referred to the Board of the Environment Protection Authority (the Board) for assessment under the Environmental Management and Pollution Control Act 1994 (EMPCA).​

​Notice of Intent 

 Forico Pty Limited, Hummocks Quarry, Upgrade from Level 1 to Level 2 activity - NOI (PDF 297Kb)

​Environmental Effects Report Guidelines

EER Guidelines have been prepared by the Board to assist the proponent to prepare a case for assessment. Based on the information contained in the Notice of Intent, the guidelines identify the key issues which are expected to be relevant to the assessment of the proposal.

 Forico Pty Limited, Hummocks Quarry, Upgrade from Level 1 to Level 2 activity - EER Guidelines (PDF 254Kb)

Public Exhibition of Documentation

A copy of the permit application and all plans and other documentation submitted with the permit application (including the EER) were made available for public inspection. The public consultation period has now closed.​

​The purpose of the EER is to provide a source of information upon which interested individuals, groups, government agencies and the Board may consider the environmental impacts of the proposal.

The EER was prepared by the proponent on the basis of the Project Specific Guidelines for preparation of an EER which were provided by the Board.​

 Forico Pty Limited, Hummocks Quarry, Upgrade from Level 1 to Level 2 activity - EER (PDF 58Mb)