Current Stage
Public Comment Closed on Case for Assessment
Proposal Details
Client: Greenham Tasmania Pty Ltd
Premises: Smithton Abattoir
Activity: an abattoir
Class of Assessment: 2A
Important Dates
Assessment Commenced: 14/3/2025
Case for Assessment Opened for Public Comment: 10/10/2026
Case for Assessment Closed for Public Comment: 26/10/2026
The Proposal
Greenham Tasmania Pty Ltd is proposing to construct replacement operational facilities and demolish redundant infrastructure at the Smithton Abattoir, located off the Bass Highway, approximately 1.5km south of Smithton. There is no change in production volumes proposed.
The proponent has lodged a Permit
Application with a supporting Environmental Effects Report (EER) to Circular Head Council.
The application was referred to
the Board of the Environment Protection
Authority (the Board) for assessment under
the Environmental Management and Pollution Control Act
1994 (EMPCA).
Notice of Intent
Greenham Tasmania Pty Ltd, Greenham Smithton Facility Upgrade, Smithton Abattoir - NOI (PDF 353Kb)
Greenham Tasmania Pty Ltd, Greenham Smithton Facility Upgrade, Smithton Abattoir - NOI Appendices (PDF 59Mb)
Environmental Effects Report Guidelines
EER Guidelines have been prepared by the Board to assist the proponent to prepare a case for assessment. Based on the information contained in the Notice of Intent, the guidelines identify the key issues which are expected to be relevant to the assessment of the proposal.
Greenham Tasmania Pty Ltd, Greenham Smithton Facility Upgrade, Smithton Abattoir - EER Guidelines (PDF 399Kb)
Public
Exhibition of Documentation
A copy of the permit application
and all plans and other documentation submitted with the permit application
(including the EER) were made available for public inspection. The public consultation period has now closed.
Environmental Effects
Report
The purpose of the EER is to provide a source of
information upon which interested individuals, groups, government agencies and
the Board may consider the environmental impacts of the proposal.
The EER was prepared by the proponent on the basis of the
Project Specific Guidelines for preparation of an EER which were provided by the Board.
Greenham Tasmania Pty Ltd, Greenham Smithton Facility Upgrade, Smithton Abattoir- EER (PDF 7Mb)
Greenham Tasmania Pty Ltd, Greenham Smithton Facility Upgrade, Smithton Abattoir - Appendices (PDF 51Mb)