H.B.M.I. Pty Ltd, Leslie Vale Quarry, Capacity Increase

Current Stage

Public Comment Closed on Draft Guidelines

Proposal Details

Client: H.B.M.I. Pty Ltd

Premises: Leslie Vale Quarry

Activity: a quarry

Class of Assessment: 2C

Important Dates

Assessment Commenced: 2/5/2022

Draft Guidelines Opened for Public Comment: 15/4/2023

Draft Guidelines Closed for Public Comment: 1/5/2023

​Status: Final Guidelines issued, awaiting EIS​

​​​​​​​​The Proposal​

The owners of the existing quarry propose to increase the extractive capacity from 583,000 m3 to 1,250,000 m3. This will entail intensification of existing activities, more frequent blasting, extending hours of operation for most activities and taking secondary crushing, loading, and trucking to 24 hour operations. The proposal footprint includes roughly 30 ha of current native vegetation and roughly 100 ha of land to be disturbed above what is currently approved under the existing permit.​​

The proponent intends to lodge a permit application with Kingborough Council under the Land Use Planning and Approvals Act 1993. The proposal will be subject to an environmental impact assessment by the Board of the EPA (the Board) in accordance with the Environmental Management and Pollution Control Act 1994 (EMPC Act).

EIS Guidelines 

EIS Guidelines have been prepared by the Board to assist the proponent to prepare the case for assessment. Based on the information contained in the Notice of Intent, the guidelines identify the key issues which are expected to be relevant to the assessment of the proposal.

Public comment was invited on the draft guidelines, the comment period has now closed. The final guidelines have been issued to the proponent.​

 H.B.M.I. Pty Ltd, Leslie Vale Quarry, Capacity Increase - Final EIS Guidelines (PDF 537Kb)

​​​​Notice of Intent

 H.B.M.I. Pty Ltd, Leslie Vale Quarry, Capacity Increase - NOI (PDF 2Mb)