Client: Kermandie Hire Pty Ltd
Premises: Stanmore Quarry
Activity: a quarry and materials handling
Class of Assessment: 2A
Important Dates
Assessment Commenced: 22/8/2022
The Proposal
The proposal is to increase the operating and production capacity of the existing quarry north of Dover from 5,000m3 per year to 20,000m3 per year with the introduction of up to two mechanical crushers onsite.
Notice of Intent
Kermandie Hire Pty Ltd, Stanmore Quarry Capacity Increase, Huon Highway, Dover - NOI (PDF 2Mb)
Environmental Effects Report Guidelines
EER Guidelines have been prepared by the Board to assist the proponent to prepare a case for assessment. Based on the information contained in the Notice of Intent, the guidelines identify the key issues which are expected to be relevant to the assessment of the proposal.
Kermandie Hire Pty Ltd, Stanmore Quarry Capacity Increase, Huon Highway, Dover - EER Guidelines (PDF 5Mb)