Current Stage
Assessment Completed
Proposal Details
Client: Roadways Pty Ltd
Premises: 1 Parkholme Drive, Bridgewater 7030
Activity: Pre-mix bitumen plant
Class of Assessment: 2A
Important Dates
Assessment Commenced: 18/2/2020
Case for Assessment Opened for Public Comment: 21/10/2020
Case for Assessment Closed for Public Comment: 5/11/2020
Assessment Completed: 11/12/2020
The Proposal
Roadways Pty Ltd (Ian Harrington Group) has proposed to increase production to 70,000 tonnes per annum at their pre-mix bitumen plant located at 1 Parkholme Drive, Bridgewater.
The proponent has lodged a Development Application with a supporting Environmental Effects Report (EER) to Brighton Council.
The application was referred to the Board of the
Environment Protection Authority (the Board) for assessment under the
Environmental Management and Pollution Control Act 1994 (EMPCA).
Public Exhibition of Documentation
A copy of the permit application and all plans and other documentation submitted with the permit application (including the EER) were made available for public inspection. The public consultation period has now closed.
Environmental Effects Report
The purpose of the EER is to provide a source of information upon which interested individuals, groups, government agencies and the Board may consider the environmental impacts of the proposal.
The EER was prepared by the proponent on the basis of the project specific guidelines for preparation of an EER which were provided by the Board.
Roadways Pty Ltd, Asphalt Plant Increase in Production, Bridgewater - EER
(2Mb)
Environmental Assessment Report and EPA Decision
The environmental assessment report has now been completed and can be viewed below. The report contains the permit conditions required by the Board to be included in the land use permit, if a permit is granted, by Council.
Roadways Pty Ltd, Asphalt Plant Increase in Production, Bridgewater - EAR
(1Mb)