Walters Contracting Pty Ltd, Union Bridge Gravel Pit, Mole Creek

Current Stage

Assessment Completed

Proposal Details

Client: Walters Contracting Pty Ltd

Premises: Union Bridge Quarry, Mole Creek 7304

Activity: Quarry

Class of Assessment: 2A

Important Dates

Assessment Commenced: 22/2/2018

Case for Assessment Opened for Public Comment: 1/12/2018

Case for Assessment Closed for Public Comment: 15/12/2018

Assessment Completed: 1/2/2019

​The Proposal

Walters Contracting Pty Ltd has proposed an increase in production at Union Bridge Quarry, Mole Creek, from 20,000 m3 up to 50,000 m3 of product extracted, crushed and screened per year.

The proponent has lodged a Development Application with a supporting Environmental Effects Report (EER) to Kentish Council.

The application was referred to the Board of the Environment Protection Authority (the Board) for assessment under the Environmental Management and Pollution Control Act 1994 (EMPCA).

Public Exhibition of Documentation and Public Representations​

A copy of the permit application and all plans and other documentation submitted with the permit application was made available for public inspection. The public comment period is now closed.​

Environmental Effects Report

The purpose of the EER is to provide a source of information upon which interested individuals, groups, government agencies and the Board may consider the environmental impacts of the proposal.

The EER was prepared by the proponent on the basis of the project specific guidelines for preparation of an EER which were provided by the Board.

Walters Contracting Pty Ltd, Union Bridge Gravel Pit, Mole Creek - EER

Walters Contracting Pty Ltd, Union Bridge Gravel Pit, Mole Creek - Appendices Part A

Walters Contracting Pty Ltd, Union Bridge Gravel Pit, Mole Creek - Appendices Part B

Walters Contracting Pty Ltd, Union Bridge Gravel Pit, Mole Creek - Appendices Part C

Environmental Assessment Report and EPA Decision

The environmental assessment report has now been completed and can be viewed below. The report contains the permit conditions required by the Board to be included in the land use permit, if a permit is granted, by Council.

Walters Contracting Pty Ltd, Union Bridge Gravel Pit, Mole Creek - EAR